GOLF COURSE UPDATE
·
Mowing Heights: GRNS .115,
Tees/Collars/Approaches .375, FWYS .400, Step-cut 1”, RGH 2.25”
·
Mowing Schedule: Greens-daily and double rolled unless
weather dictates otherwise Wed./Fri./Sat./Sun., Tees/Approaches/FWYS Mon./Wed./Fri.,
Rough/Bunkers-twice throughout the week
·
ROUGH DEBATE – GREENSPEED DEBATE
·
No issues with playing surfaces due to stress or
mechanical damage heading into August.
·
Aeration on-schedule and will continue to pursue
20 to 25% surface area disruption according to ISTRC testing performed.
·
Pine Hollow Green’s Department Blog:
pinehollowgreens.blogspot.com
2016 FALL PROJECTS
(IN-HOUSE)
·
Tee re-leveling #17 white, #18 white, #2 left
black/white.
·
Continue with bunker sand removal and
replacement all fairway bunkers.
·
Addition of Nursery Green behind #3/#15 and
screened out by fescue.
·
Improve contours in fairways and green expansion
areas with additions and subtractions.
·
Improve and expand practice area with tree
removal, bunker rebuild, and fairway expansion.
·
In-house drainage installation at chipping area approach
(driving range).
·
Continue with property cleanup including tennis
area, parking lot, and shop improvements.
PROPOSED PROJECTS
·
GOLF
COURSE –Cont. Tree Maintenance Plan for 2016/2017 late fall to winter:
In/Out House.
·
GOLF
COURSE- Tee Complex Construction #11 (In-House) and #12/#14 (Out-House).
·
PRACTICE
AREA- New synthetic surface for driving range mat w/ re-leveled and re-grassed.
·
PRACTICE
AREA- Rebuild bunker at Chipping Green with the addition of more fairway
height for longer pitch and run options.
·
LANDSCAPE-Area
behind and left of #7 GREEN planted w/ 5-7’ Cedars to screen out maintenance
dump and service road.
·
LANDSCAPE-Move
and relocate trees from golf course to specific areas on property.
·
EQUIPMENT-
Lease packages have been built to address current concerns while updating
our fleet of deteriorating equipment.
·
BUDGET- Equipment
and Resources to continue to improve the Club’s biggest asset.